Project SSE – Activated Carbon Dosing Plant using Silo for Tanker Deliveries

The site generated power from a mixed solid fuel source and an issue with dioxins was identified. As a known best available technology with a proven track record, PAC or powdered activated carbon was chosen to inject into the main flue before the existing bag house filter. The Solution The story of this project began […]

Read More… from Project SSE – Activated Carbon Dosing Plant using Silo for Tanker Deliveries

Project WA – Hot Gas Filter for Aluminium Furnace, Sodium Bicarbonate Injection via Bulk Bag and Spark Detection System

Problem Taking scrap Aluminium and melting down in a furnace to produce specification aluminium ingots produces fume and smoke. The local authority had recognised that an improvement to the direct extraction to atmosphere could be made. It is currently more profitable to buy in ‘dirty’ aluminium scrap to process which produces the most fume and […]

Read More… from Project WA – Hot Gas Filter for Aluminium Furnace, Sodium Bicarbonate Injection via Bulk Bag and Spark Detection System

Project UK5 – CleanPulse Bag Filter with Sodium Bicarbonate Sorbent Injection System for Flue Gas Treatment

From initial enquiry to completion of installation this project extended over 24 months. The requirement was for a gas cleaning plant to remove toxic gases from a new process on a float glass line. The bag filter and sorbent injection systems are last in line after oxidiser and boiler. Supply Highlights Pulse Jet Filter Design […]

Read More… from Project UK5 – CleanPulse Bag Filter with Sodium Bicarbonate Sorbent Injection System for Flue Gas Treatment

Project NE – Phase 1 – A Complete Waste to Energy FGT Plant from Economiser Outlet to Stack

Programme   Engineering Order date: February 2012 Full Order date: March 2012 Installation commenced: May 2012 Substantial completion: December 2012 (7 months) Commissioning commenced: January 2013 This project ordered in February 2012 involves all of the elements of a flue gas treatment plant and was installed as part of an innovative new build Advanced Thermal […]

Read More… from Project NE – Phase 1 – A Complete Waste to Energy FGT Plant from Economiser Outlet to Stack

Project AR – High Temperature CleanPulse Filter with Offline Cleaning, Online Maintenance and a Spark Detection System

Project AR From initial enquiry to completion of installation this project extended over 3 years, although the installation was achieved in 8 weeks to a tight changeover schedule. The requirement was for a replacement filter plant with offline cleaning, online maintenance to remove waste dust from two Aluminium Recycling Furnaces utilising the clients existing sodium […]

Read More… from Project AR – High Temperature CleanPulse Filter with Offline Cleaning, Online Maintenance and a Spark Detection System

Project LE – Complex Ducting System Design and Installation in Scotland

Problem Working through a third party in the UK, we were invited to provide services to design supply and install various elements of a biomass fired furnace. The plant used a combined heat and power plant and generated electricity via the Organic Rankine Cycle. Filter Designs scope included ducting, fans, chimney, insulation and erection. A […]

Read More… from Project LE – Complex Ducting System Design and Installation in Scotland

Project SF – Retractable Extraction Canopy for Steel Lancing

The company, now in its third century and probably the oldest steel business in the world, remains at the forefront of technology for castings and forgings for heavy engineering across the world. As both individuals and a company, Sheffield Forgemasters has never been more aware of its environmental impact and the ongoing responsibility to reduce […]

Read More… from Project SF – Retractable Extraction Canopy for Steel Lancing

Project FFH – Dual CleanPulse Bag Filter with Trend BMS Controls for the NHS

Dual Cle Summary Three coal-fired boilers at Fairfield Hospital in Bury, Manchester provide steam for hospital heating, cleaning and surgical needs. The continuous operation of these boilers is therefore critical. The boilers emitted their waste gases to atmosphere which included some large particles which affected the local area during periods of heavy smoke output. The […]

Read More… from Project FFH – Dual CleanPulse Bag Filter with Trend BMS Controls for the NHS

Project AS – Two CleanPulse Ceramic Filters for Export to Singapore

Note: A signed confidentiality agreement prevents us disclosing further detail of this project. A worldwide household name required 2 gas treatment systems to operate in a pilot plant that is required to be operational for a minimum 8400 hours (360 days) per annum. Most importantly this application involved a usually hot gas inlet temperature of […]

Read More… from Project AS – Two CleanPulse Ceramic Filters for Export to Singapore

Project PB – Large CleanPulse Bag Filter with Sodium Bicarbonate Silo, Wet Ash De-duster, CEMS and Chimney

Heineken UK – Royal Brewery, Manchester and John Smith’s Brewery, Tadcaster Spent Grain from Royal Brewery Manchester At the Royal Brewery in Manchester, U.K., green beer is not just for St. Patrick’s Day. Soon all the beer produced by the plant will be “green,” thanks to a new energy efficient combined-heat-and-power system (CHP) fuelled by […]

Read More… from Project PB – Large CleanPulse Bag Filter with Sodium Bicarbonate Silo, Wet Ash De-duster, CEMS and Chimney

Our recent Projects

An empty warehouse is always a welcome place to start a project.  This is because we have a blank canvas with which to design an ideal layout for a flue gas treatment plant.  Once installed, our system cleans the gases from a waste boiler and waste infeed plant and will allow the end user to stop transporting waste around the country and manage it locally, save on transport costs and produce some electricity too.

Project VC - Turnkey Flue Gas Treatment Plant for Waste Boiler

Project JP2 - Complete Flue Gas Treatment System for Intumescent Paint Furnaces (Phase 2)

Filter Designs is a trading name of Turnkey Filtration Limited, a limited liability company registered
in England under number 16279255, whose registered office is at Filtration House, Farndon Road, Market Harborough,
LE16 9NP - Website by 1PCS